What is the difference between fixed price and time & material?
With a fixed price, a clearly described scope is delivered for an agreed total price; the cost risk lies with the contractor. With time & material, billing is based on actual effort; flexibility and budget risk lie more with the client. Which model fits depends on how clear the requirements are.

The two models at a glance
With a fixed price, client and contractor agree in advance on what is delivered and what it costs. If the work turns out to be more laborious than expected, the extra effort stays with the provider in principle, but the scope must then be described unambiguously. In Germany, such a project is generally treated as a contract for work (Werkvertrag).
With time & material (T&M, billing by effort), the client pays for the hours or days actually worked at agreed rates, often with monthly invoicing. The model is closer to a service contract (Dienstvertrag): what is owed is the work performed, not a specific result. The legal classification, however, depends on the specific contract.
Advantages, disadvantages and hybrid forms
A fixed price offers planning certainty but requires a precise description of the work. Changes are renegotiated through change requests, and providers build in risk premiums. T&M is flexible and suits projects whose scope only becomes clear along the way; in return, the client needs budget control and regular transparency.
In between are hybrid forms: a fixed price for a clearly defined phase such as concept or first release, T&M with a budget cap, a fixed price per sprint, or a framework agreement with an hours package for maintenance and further development. Which variant fits depends less on the price than on how sure you are today of what will be needed in the end.
- Requirements clear and stable: fixed price
- Requirements open or still emerging: T&M with a budget frame
- New idea, uncertain market: first a small fixed price for a concept or MVP
- Ongoing maintenance and development: hours or monthly package
- In every case: put scope, acceptance and change process in writing
Real-world example: two projects at a supplier
A supplier has two projects carried out. For connecting its inventory management to accounting software, a specification and test cases exist. A fixed price makes sense here, because scope and outcome are clear and both sides know exactly what is delivered. Change requests are the exception.
The second project is a customer portal whose functions only become clear with the first users. It starts with a fixed price for concept and prototype, then continues in stages by effort with a fixed monthly budget. The supplier keeps an eye on the costs and can adjust at any time.
Common mistakes and implementation
Common mistakes are a fixed price for a project with unclear requirements, which later triggers disputes over scope; T&M without a budget limit and status reports; unclear rules for acceptance and changes; and comparing by price alone instead of by the scope included. Both models work when work, changes and acceptance are clearly regulated.
For clearly defined projects, Nano Concepts offers packages—Starter from €2,500, Professional from €8,000, Enterprise (custom)—and for larger projects we agree the billing by scope and effort with you. You should have the legal consequences reviewed in each individual case. This article does not replace legal advice.
Frequently asked questions about Fixed price vs. time & material
Neither is better in general. A fixed price suits clearly described projects and provides budget certainty. Billing by effort suits projects whose requirements are still developing. A combination with a budget frame is often the most sensible solution.
Changes outside the agreed scope are assessed as a change request: the provider estimates effort and schedule, and you decide whether to approve. That way the fixed price for the base scope is preserved, and additional work is agreed transparently.
Time & material means billing for the working time actually spent and the materials or costs incurred, at agreed daily or hourly rates. Timesheets and a budget cap are common, so that the client keeps track of costs.
Matching services

Custom Software
Software built around your workflows instead of standard tools with compromises – for replacing Excel, internal tools and specialized business applications.
Learn more
Software Development
Software from requirements to operations – web, mobile and integrations from a single source.
Learn more
MVP Development
The first working version of your software or app – focused on the core features and quickly testable with real users.
Learn more
Technology Consulting
Software selection, architecture, code review and a digitalization roadmap – independent and implementation-oriented.
Learn moreRelated terms
Relevant for these industries
Related magazine articles

Scrum in Software Projects: Roles, Process and Velocity
Scrum makes progress visible – when the Product Owner can make decisions, the Definition of Done applies and velocity serves as an internal planning tool. A guide for clients commissioning custom software.
Read more
Software Requirements Specification (Lastenheft): Structure, Example and Checklist
A good requirements specification makes quotes comparable and fixed prices possible. How it is structured, how to word requirements so they can be tested and how to tell that yours is complete.
Read more
Prioritizing Technical Debt: Pay the Interest or Pay It Down?
Technical debt is not a synonym for bad code – it becomes dangerous when it stays invisible. Here is how to assess legacy burdens by impact and effort and reduce them in a plannable way.
Read more